Satellite and drone imagery show severe delays in U.S. data center construction



Silicon Valley has been investing hundreds of billions of dollars to build ever-larger artificial intelligence data centers that require as much power as hundreds of thousands of U.S. homes, but large-scale construction faces huge construction and power challenges and growing local resistance. Satellite images now show that nearly 40% of data center projects in the United States may not be completed as planned this year.

this financial times Satellite imagery using geospatial data analysis company SynMax shows the progress of each data center project in clearing land and laying foundations. It also cross-checked project progress against public statements and licensing documents prepared by industry research group IIR Energy. The resulting analysis revealed that major projects at technology companies such as Microsoft, Oracle and OpenAI “could be delayed by more than three months from completion dates.”

According to the Financial Times, interviews with more than a dozen industry executives highlighted delays caused by “chronic shortages of labour, power and equipment” at data centers and the process of obtaining necessary permits. Managers involved in construction Open artificial intelligence The project specifically mentioned that there were not enough tradespeople (such as electricians and pipefitters) to work on multiple data center projects.

The massive power demands of planned data center construction also pose a significant energy bottleneck, especially as utilities struggle to build adequate generation facilities and expand the power infrastructure needed to provide more power. Tariffs imposed on imported equipment from China such as transformers only make the situation worse For Silicon Valley’s artificial intelligence ambitions.



Source link

Leave a Reply

Your email address will not be published. Required fields are marked *